Project Details

Project Details
Agency King Co. Parks
Project # 2017155
Project Title Wilburton Trestle
WSDOT Region Northwest
Legislative District 041, 048
Congressional District 09
Project Description Convert the Wilburton Trestle into a multipurpose, elevated trail.
Project Type Transportation Enhancement
Project Funding
Fund ProgramAmount
MAW Tier Bike/Ped$6,000,000.00
State Legislature Earmarks$2,500,000.00
State Total$8,500,000.00
Other$18,110,465.00
Total Project Cost (see NOTE below)$26,610,465.00
Project Milestones
Preliminary Engineering Authorized
Environmental Approved 10-24-2022
Right of Way Certified
Construction Authorized 09-12-2023
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.