Project Details

Project Details
Agency Stevens Co.
Project # F334002
Project Title Arden Bridge
WSDOT Region Eastern
Legislative District 007
Congressional District 05
Project Description New concrete girder bridge to replace existing bridge. Roadway approaches and safety features will be upgraded.
Project Type Bridge
Project Funding
Fund ProgramAmount
Bridge$3,770,265.00
Federal Total$3,770,265.00
Other$40,000.00
Total Project Cost (see NOTE below)$3,810,265.00
Project Milestones
Preliminary Engineering Authorized 10-12-2018
Environmental Approved 08-17-2021
Right of Way Certified 05-17-2022
Construction Authorized 08-15-2022
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.