Project Details

Project Details
Agency Blaine
Project # 5635001
Project Title Boblett St Channelization & Corridor
WSDOT Region Northwest
Legislative District 042
Congressional District 01
Project Description Construct roundabout, channelization, sidewalk replacement, and drainage.
Project Type Preservation
Project Funding
Fund ProgramAmount
Carbon Reduction$395,288.00
STP Regional$1,327,055.00
Federal Total$1,722,343.00
Other$2,877,770.00
Total Project Cost (see NOTE below)$4,600,113.00
Project Milestones
Preliminary Engineering Authorized 09-22-2017
Environmental Approved 12-03-2020
Right of Way Certified 09-18-2023
Construction Authorized 01-05-2024
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.