Project Details

Project Details
Agency Pierce Co.
Project # 3170004
Project Title Canyon Rd-Pioneer to 52nd (FAST)
WSDOT Region Olympic
Legislative District 029
Congressional District 09
Project Description Extend Canyon Road East from Pioneer Way East to 52nd Street by constructing a new 4 to 5 lane roadway, realigning intersection adding an overpass at BNSF tracks, bike and ped facilities and stormwater system. This project was originally part of STPUL-3170(003) which has been revised to exclude this section of the Canyon Road improvements.
Project Type Design
Project Funding
Fund ProgramAmount
National Corridor (NCPD)$2,500,000.00
STP Regional$3,319,000.00
Federal Total$5,819,000.00
Other$908,168.00
Total Project Cost (see NOTE below)$6,727,168.00
Project Milestones
Preliminary Engineering Authorized 08-12-2002
Environmental Approved 03-17-2017
Right of Way Certified
Construction Authorized
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.