Project Details

Project Details
Agency Columbia Co.
Project # D071006
Project Title Kellogg Hollow - Phase 4
WSDOT Region South Central
Legislative District 009
Congressional District 05
Project Description Shoulder repair/widening, pavement repair, HMA overlay, striping, and guardrail.
Project Type Preservation
Project Funding
Fund ProgramAmount
STP Regional$3,591,000.00
Federal Total$3,591,000.00
Other$0.00
Total Project Cost (see NOTE below)$3,591,000.00
Project Milestones
Preliminary Engineering Authorized 06-17-2026
Environmental Approved 06-02-2026
Right of Way Certified
Construction Authorized 09-02-2026
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.