Project Details

Project Details
Agency Lincoln Co.
Project # FFEX003
Project Title Duck Lake Rd
WSDOT Region Eastern
Legislative District 009
Congressional District 05
Project Description Realign the horizontal and vertical alignments, reconstruct subgrade to ensure flatter slopes, upgrade and/or replace drainage facilities. Place crushed surfacing along with a bituminous surface treatment including a construction seal.
Project Type Preservation
Project Funding
Fund ProgramAmount
Federal Funds Exchange$841,559.66
State Total$841,559.66
Other$3,490,765.34
Total Project Cost (see NOTE below)$4,332,325.00
Project Milestones
Preliminary Engineering Authorized
Environmental Approved 07-08-2025
Right of Way Certified
Construction Authorized 03-30-2026
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.