Project Details

Project Details
Agency Auburn
Project # 1059003
Project Title C St SW Preservation (GSA Signal to Ellingson Rd)
WSDOT Region Northwest
Legislative District 030
Congressional District 09
Project Description Grind and overlay the roadway and install ADA upgrades to curb ramps and pedestrian push buttons.
Project Type Preservation
Project Funding
Fund ProgramAmount
STP Regional$1,025,996.00
Federal Total$1,025,996.00
Other$178,076.00
Total Project Cost (see NOTE below)$1,204,072.00
Project Milestones
Preliminary Engineering Authorized
Environmental Approved 03-09-2023
Right of Way Certified
Construction Authorized 12-02-2025
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.