Project Details

Project Details
Agency College Place
Project # 7166002
Project Title Whitman Drive Multiuse Path
WSDOT Region South Central
Legislative District 016
Congressional District 05
Project Description Construct asphalt multiuse path on south side of Whitman Drive between Davis Avenue and Whitman Drive. Includes ADA Ramps at Davis, Evans, and Academy Way.
Project Type Design
Project Funding
Fund ProgramAmount
Carbon Reduction$278,089.00
Federal Total$278,089.00
Other$43,402.00
Total Project Cost (see NOTE below)$321,491.00
Project Milestones
Preliminary Engineering Authorized 11-25-2025
Environmental Approved 09-29-2026
Right of Way Certified
Construction Authorized
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.