Project Details

Project Details
Agency Spokane Co.
Project # W325002
Project Title Day Mt. Spokane Guardrail
WSDOT Region Eastern
Legislative District 004
Congressional District 05
Project Description Install/upgrade guardrail and remove trees at spot locations.
Project Type Design
Project Funding
Fund ProgramAmount
HSIP$184,000.00
Federal Total$184,000.00
Other$0.00
Total Project Cost (see NOTE below)$184,000.00
Project Milestones
Preliminary Engineering Authorized 01-15-2026
Environmental Approved
Right of Way Certified
Construction Authorized
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed