Project Details

Project Details
Agency Poulsbo
Project # 9918024
Project Title 8th Ave Realignment Study
WSDOT Region Olympic
Legislative District 023
Congressional District 06
Project Description Study of alternatives and development of a preferred design concept and implementation plan for re-alignment of 8th Avenue NE and siting of transit oriented multi-modal hub on City of Poulsbo property near SR 305.
Project Type
Project Funding
Fund ProgramAmount
STP Regional$311,400.00
Federal Total$311,400.00
Other$48,600.00
Total Project Cost (see NOTE below)$360,000.00
Project Milestones
Preliminary Engineering Authorized 08-22-2025
Environmental Approved
Right of Way Certified
Construction Authorized
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.