Project Details

Project Details
Agency Cheney
Project # 0200807
Project Title Purchase of Electric Vehicles and Charging Station
WSDOT Region Eastern
Legislative District 006
Congressional District 05
Project Description Purchase of 7 electric vehicles to replace City of Cheney gas-powered maintenance vehicles. Purchase also includes a solar panel charging canopy.
Project Type Other
Project Funding
Fund ProgramAmount
Carbon Reduction$315,654.00
STP Regional$26,519.00
Federal Total$342,173.00
Other$63,245.00
Total Project Cost (see NOTE below)$405,418.00
Project Milestones
Preliminary Engineering Authorized
Environmental Approved 04-01-2025
Right of Way Certified
Construction Authorized 08-12-2025
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.