Project Description Construct school or playground 20-mph speed zone with flashing beacons and signage, ADA curb ramps, sidewalk, shared-use-path, roundabout, raised intersection, and curb extensions.
Project Type Design
Project Funding
Fund ProgramAmount
Safe Routes to School$153,000.00
State Total$153,000.00
Other$9,000.00
Total Project Cost (see NOTE below)$162,000.00
Project Milestones
Preliminary Engineering Authorized 09-15-2025
Environmental Approved
Right of Way Certified
Construction Authorized
Completed