Project Details

Project Details
Agency Bellevue
Project # 2032140
Project Title Main St Multipurpose Pathway
WSDOT Region Northwest
Legislative District 041, 048
Congressional District 01
Project Description Construct multi-use pedestrian and bicycle pathway along Main Street. Includes planter, traffic calming features including raised crosswalks, new and relocated crosswalks, signal modifications, ADA curb ramp upgrades, updated green pavement markings, and landscaping.
Project Type Transportation Enhancement
Project Funding
Fund ProgramAmount
TAP$2,508,764.00
Federal Total$2,508,764.00
Other$1,098,305.00
Total Project Cost (see NOTE below)$3,607,069.00
Project Milestones
Preliminary Engineering Authorized
Environmental Approved 12-20-2023
Right of Way Certified 06-25-2025
Construction Authorized 07-08-2025
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.