Project Details

Project Details
Agency Port of Klickitat
Project # 2025058
Project Title Dallesport Industrial Park Rail Spur
WSDOT Region Southwest
Legislative District 014
Congressional District 04
Project Description Improve the rail spur infrastructure at the Dallesport Industrial dock to allow train traffic to use the rail line.
Project Type Safety
Project Funding
Fund ProgramAmount
Freight Mobility$221,000.00
State Total$221,000.00
Other$16,272.00
Total Project Cost (see NOTE below)$237,272.00
Project Milestones
Preliminary Engineering Authorized
Environmental Approved 03-26-2026
Right of Way Certified
Construction Authorized 05-04-2026
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed