Project Details

Project Details
Agency Auburn
Project # 1069010
Project Title A St SE (37th St SE to Lakeland Hills Way)
WSDOT Region Northwest
Legislative District 030, 031
Congressional District 08
Project Description Grind and overlay the roadway and install ADA upgrades to curb ramps and pedestrian push buttons.
Project Type Preservation
Project Funding
Fund ProgramAmount
STP Regional$811,412.91
Federal Total$811,412.91
Other$126,636.71
Total Project Cost (see NOTE below)$938,049.62
Project Milestones
Preliminary Engineering Authorized
Environmental Approved 11-27-2023
Right of Way Certified
Construction Authorized 04-02-2025
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed