Project Details

Project Details
Agency Lakewood
Project # 3084011
Project Title 112th Street SW - S Tacoma Way to Steele St S
WSDOT Region Olympic
Legislative District 029
Congressional District 10
Project Description Rehabilitate 112th Street S from S Tacoma Way to Steele St S. Includes pavement repair, grind, overlay, and channelization.
Project Type Preservation
Project Funding
Fund ProgramAmount
STP Regional$768,667.00
Federal Total$768,667.00
Other$467,197.00
Total Project Cost (see NOTE below)$1,235,864.00
Project Milestones
Preliminary Engineering Authorized 02-19-2025
Environmental Approved 12-04-2025
Right of Way Certified
Construction Authorized 03-23-2026
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.