Project Details

Project Details
Agency Pend Oreille Co.
Project # F260006
Project Title Usk Bridge Rehabilitation
WSDOT Region Eastern
Legislative District 007
Congressional District 05
Project Description Repair expansion joints, timber girders, timber piling, and concrete pier caps.
Project Type Bridge
Project Funding
Fund ProgramAmount
Bridge$4,773,153.00
Federal Total$4,773,153.00
Other$0.00
Total Project Cost (see NOTE below)$4,773,153.00
Project Milestones
Preliminary Engineering Authorized
Environmental Approved 01-09-2024
Right of Way Certified
Construction Authorized 09-14-2026
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.