Project Details

Project Details
Agency Covington
Project # 000S707
Project Title Systemic Pedestrian Safety
WSDOT Region Northwest
Legislative District 047
Congressional District 08
Project Description Install speed feedback signs at SE 256th Street and 156th Avenue SE, install asphalt path with extruded curb on 180th Avenue SE from SE 244th Street to Covington Community Park where existing sidewalk ends, and install RRFB and marked crosswalk improvements on 180th Avenue SE at SE 244th Street.
Project Type Safety
Project Funding
Fund ProgramAmount
HSIP$317,000.00
Federal Total$317,000.00
Other$20,049.00
Total Project Cost (see NOTE below)$337,049.00
Project Milestones
Preliminary Engineering Authorized 03-21-2025
Environmental Approved 11-19-2025
Right of Way Certified
Construction Authorized 06-10-2026
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.