Project Details

Project Details
Agency Dayton
Project # A070006
Project Title South 4th Street Overlay
WSDOT Region South Central
Legislative District 009
Congressional District 05
Project Description Grind and overlay, replacement of non-ADA compliant ADA ramps, isolated pavement repair.
Project Type Preservation
Project Funding
Fund ProgramAmount
STP Regional$2,062,220.00
Federal Total$2,062,220.00
Other$0.00
Total Project Cost (see NOTE below)$2,062,220.00
Project Milestones
Preliminary Engineering Authorized
Environmental Approved 08-16-2024
Right of Way Certified
Construction Authorized 09-17-2024
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed