Project Details

Project Details
Agency Kittitas Co.
Project # 19CN004
Project Title 2024 Vantage Highway Paving
WSDOT Region South Central
Legislative District 013
Congressional District 08
Project Description Grind and overlay of asphalt on Vantage Highway within the existing pavement limits along with temporary and permanent pavement marking for repair, rehabilitation and preservation.
Project Type Preservation
Project Funding
Fund ProgramAmount
STP Regional$1,803,201.00
Federal Total$1,803,201.00
Other$281,425.00
Total Project Cost (see NOTE below)$2,084,626.00
Project Milestones
Preliminary Engineering Authorized
Environmental Approved 08-15-2024
Right of Way Certified
Construction Authorized 09-17-2024
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.