Project Details

Project Details
Agency Port of Kalama
Project # 2024043
Project Title Industrial Rail Additions
WSDOT Region Southwest
Legislative District 020
Congressional District 03
Project Description Provide additional railroad car storage at the TEMCO facility to spot trains, preventing impacts to mainline rail traffic.
Project Type Safety
Project Funding
Fund ProgramAmount
Freight Mobility$3,585,578.00
State Total$3,585,578.00
Other$566,292.00
Total Project Cost (see NOTE below)$4,151,870.00
Project Milestones
Preliminary Engineering Authorized 12-19-2024
Environmental Approved 08-20-2025
Right of Way Certified
Construction Authorized 01-05-2026
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.