Project Details

Project Details
Agency Snohomish Co.
Project # 9931028
Project Title Schweitzer and Wisconsin Creek Bridge Rehab
WSDOT Region Northwest
Legislative District 039
Congressional District 08
Project Description Remove and replace the asphalt road surface on the concrete bridge decks at Schweitzer and Wisconsin Creek, and improve drainage.
Project Type Preservation
Project Funding
Fund ProgramAmount
Federal Lands$381,414.00
Federal Total$381,414.00
Other$59,527.00
Total Project Cost (see NOTE below)$440,941.00
Project Milestones
Preliminary Engineering Authorized 09-23-2024
Environmental Approved 09-17-2026
Right of Way Certified
Construction Authorized 07-01-2026
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.