Project Details

Project Details
Agency McCleary
Project # Z141006
Project Title S 3rd Street - Oak St to Simpson Ave
WSDOT Region Olympic
Legislative District 019
Congressional District 06
Project Description Resurface and repair existing pavement, new curb and gutter, stormwater, planting strips, sidewalks, and shared bike lanes.
Project Type Design
Project Funding
Fund ProgramAmount
STP Regional$310,000.00
Federal Total$310,000.00
Other$222,130.00
Total Project Cost (see NOTE below)$532,130.00
Project Milestones
Preliminary Engineering Authorized 04-11-2024
Environmental Approved
Right of Way Certified
Construction Authorized
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.