Project Details

Project Details
Agency Coulee City
Project # Q137004
Project Title McEntee Street
WSDOT Region North Central
Legislative District 007
Congressional District 04
Project Description Reconnect the roadway, regrade, add curb and gutter on both sides of the roadway, and add sidewalk on one side of the roadway.
Project Type Preservation
Project Funding
Fund ProgramAmount
STP Regional$795,799.00
Federal Total$795,799.00
Other$124,201.00
Total Project Cost (see NOTE below)$920,000.00
Project Milestones
Preliminary Engineering Authorized 03-14-2024
Environmental Approved 05-08-2025
Right of Way Certified
Construction Authorized 09-15-2025
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.