Agency Entiat
Project # Z904008
Project Title Entiat Way/Entiat River Road Park and Ride
WSDOT Region North Central
Legislative District 012
Congressional District 08
Project Description Work at intersection of Entiat Way and Entiat River Road includes sidewalk, crosswalks, curb and gutter, illumination, asphalt roadway overlay, and construction of Park and Ride lot with stormwater and landscaping.
Project Type Preservation
Project Funding
Fund ProgramAmount
Carbon Reduction$394,078.00
STP Regional$258,060.00
Federal Total$652,138.00
Other$614,673.00
Total Project Cost (see NOTE below)$1,266,811.00
Project Milestones
Preliminary Engineering Authorized 02-27-2024
Environmental Approved 03-26-2025
Right of Way Certified 03-17-2026
Construction Authorized 06-11-2026
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.