Project Details

Project Details
Agency Seattle Office of Planning & Community Development
Project # 1140078
Project Title Reconnect South Park
WSDOT Region Northwest
Legislative District 034
Congressional District 07
Project Description Planning study, feasibility analysis, and community engagement/visioning on potential futures (redesign, full removal, no action, etc) for the SR 99 corridor through South Park, Seattle.
Project Type
Project Funding
Fund ProgramAmount
Reconnecting Communities$1,600,000.00
Federal Total$1,600,000.00
Other$844,900.00
Total Project Cost (see NOTE below)$2,444,900.00
Project Milestones
Preliminary Engineering Authorized 02-08-2024
Environmental Approved
Right of Way Certified
Construction Authorized
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.