Project Details

Project Details
Agency Republic
Project # 0021026
Project Title Republic Pathway Phase 2
WSDOT Region Eastern
Legislative District 007
Congressional District 05
Project Description Construct pathway that begins at the existing west crosswalk and runs to the east Republic School District SR 20/SR 21 crosswalk, tying together two segments of existing pathway that parallels SR 20/SR 21.
Project Type Transportation Enhancement
Project Funding
Fund ProgramAmount
TAP$331,037.00
Federal Total$331,037.00
State Legislature Earmarks$260,000.00
State Total$260,000.00
Other$0.00
Total Project Cost (see NOTE below)$591,037.00
Project Milestones
Preliminary Engineering Authorized 11-21-2023
Environmental Approved 10-01-2024
Right of Way Certified
Construction Authorized 06-13-2025
Completed