Project Details

Project Details
Agency Hatton
Project # 0555002
Project Title Hatton Bridge
WSDOT Region Eastern
Legislative District 009
Congressional District 04
Project Description Replace deck, girders, and railing.
Project Type Design
Project Funding
Fund ProgramAmount
Bridge$208,168.00
Federal Total$208,168.00
Other$0.00
Total Project Cost (see NOTE below)$208,168.00
Project Milestones
Preliminary Engineering Authorized 02-20-2024
Environmental Approved 09-29-2026
Right of Way Certified
Construction Authorized
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.