Agency Ferry Co.
Project # 2010045
Project Title East Silver Creek Bridge
WSDOT Region Eastern
Legislative District 007
Congressional District 05
Project Description Replace existing structure with a steel bridge.
Project Type Bridge
Project Funding
Fund ProgramAmount
Bridge$1,774,000.00
Federal Total$1,774,000.00
Other$1,760,000.00
Total Project Cost (see NOTE below)$3,534,000.00
Project Milestones
Preliminary Engineering Authorized
Environmental Approved 11-17-2023
Right of Way Certified
Construction Authorized 09-03-2024
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed