Project Details

Project Details
Agency Chelan Co.
Project # 9904019
Project Title Easy St and School St Intersection
WSDOT Region North Central
Legislative District 012
Congressional District 08
Project Description Construct roundabout, install luminaires, ensure pedestrian facilities meet ADA, improve drainage, and other safety improvements.
Project Type Design,Safety
Project Funding
Fund ProgramAmount
Carbon Reduction$22,076.00
HSIP$370,000.00
STP Regional$750,000.00
Federal Total$1,142,076.00
Other$1,392,924.00
Total Project Cost (see NOTE below)$2,535,000.00
Project Milestones
Preliminary Engineering Authorized 04-01-2024
Environmental Approved 08-04-2025
Right of Way Certified 07-10-2026
Construction Authorized 09-02-2026
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.