Project Description Scarify the existing deck surfaces and seal existing cracks with a thin overlay on the following structures: Roosevelt Overpass, Rock Creek, Wahkiacus Horseshoe, Forest Highway, and Miller.
Project Type Bridge
Project Funding
Fund ProgramAmount
Bridge$551,575.00
Federal Total$551,575.00
Other$0.00
Total Project Cost (see NOTE below)$551,575.00
Project Milestones
Preliminary Engineering Authorized 09-22-2023
Environmental Approved 02-20-2025
Right of Way Certified
Construction Authorized 09-15-2025
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed