Project Details

Project Details
Agency Snohomish Co.
Project # 2585001
Project Title 36th/35th Avenue W
WSDOT Region Northwest
Legislative District 021
Congressional District 01
Project Description Widen roadway between 164th St SW and 148th St SW to add center lane and bicycle lanes. Includes sidewalk and curb and gutter. Overlay roadway from 148th St SW to SR 99. Section between 164th and 156th is federally funded. Section between 156th and SR 99 funded with non-federal funds.
Project Type Improvement
Project Funding
Fund ProgramAmount
STP Regional$2,580,000.00
Federal Total$2,580,000.00
Other$5,043,782.00
Total Project Cost (see NOTE below)$7,623,782.00
Project Milestones
Preliminary Engineering Authorized
Environmental Approved 06-30-2022
Right of Way Certified 07-25-2023
Construction Authorized 08-11-2023
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.