Project Details

Project Details
Agency Port Orchard
Project # SR23013
Project Title Sidney Rd Non-Motorized (SR-16 to Hovde)
WSDOT Region Olympic
Legislative District 026
Congressional District 06
Project Description New marked crosswalk, crossing advance stop bars, Rectangular Rapid Flashing Beacon (RRFB's), pedestrian scale crossing illumination, ADA curb ramps, sidewalk with curb, sidewalk with curb and buffer, and bike lanes.
Project Type Transportation Enhancement
Project Funding
Fund ProgramAmount
Safe Routes to School$1,394,750.00
State Total$1,394,750.00
Other$2,267,134.00
Total Project Cost (see NOTE below)$3,661,884.00
Project Milestones
Preliminary Engineering Authorized 03-20-2024
Environmental Approved 12-04-2024
Right of Way Certified
Construction Authorized 06-25-2025
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.