Project Details

Project Details
Agency Des Moines
Project # SR23007
Project Title North Hill Elementary Walkway
WSDOT Region Northwest
Legislative District 033
Congressional District 09
Project Description Median refuge island, new marked crosswalk, rectangular rapid flashing beacon (RRFB), lane width reduction, speed feedback signs, ADA curb ramps, bike lanes, sidewalk (6'+) with curb
Project Type Design,Right of Way,Transportation Enhancement
Project Funding
Fund ProgramAmount
Safe Routes to School$3,000,000.00
State Total$3,000,000.00
Other$1,861,195.00
Total Project Cost (see NOTE below)$4,861,195.00
Project Milestones
Preliminary Engineering Authorized 12-12-2023
Environmental Approved 09-05-2023
Right of Way Certified
Construction Authorized
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.