Project Details

Project Details
Agency Port Orchard
Project # PB23015
Project Title Tremont St Non-Motorized Ph. 2 & 3 Development
WSDOT Region Olympic
Legislative District 026
Congressional District 06
Project Description Community Engagement Events, Pedestrian/Bicyclist Counts, Conflict analysis, Planning/analyzing pedestrian/bicyclist networks, Level of Stress Analysis, Route Directness Analysis, Preliminary Pedestrian/Bicyclist Safety Plan Analysis.
Project Type Other
Project Funding
Fund ProgramAmount
Pedestrian & Bicycle Safety$732,000.00
State Total$732,000.00
Other$0.00
Total Project Cost (see NOTE below)$732,000.00
Project Milestones
Preliminary Engineering Authorized 09-12-2024
Environmental Approved
Right of Way Certified
Construction Authorized
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.