Project Details

Project Details
Agency Fife
Project # MAWA016
Project Title Interurban Trail Extension to Puyallup
WSDOT Region Olympic
Legislative District 025
Congressional District 06
Project Description Construct curb and gutter, landscape planter, sidewalk, underground distribution power, and street lighting along 20th Street E from existing infrastructure improvements located in the 6800 block to the intersection at 70th Avenue E & Wapato Way E.
Project Type Transportation Enhancement
Project Funding
Fund ProgramAmount
MAW Tier Bike/Ped$1,400,000.00
State Total$1,400,000.00
Other$424,252.00
Total Project Cost (see NOTE below)$1,824,252.00
Project Milestones
Preliminary Engineering Authorized 08-29-2024
Environmental Approved 06-04-2025
Right of Way Certified
Construction Authorized 08-21-2026
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.