Project Details

Project Details
Agency Waitsburg
Project # Q362003
Project Title Bolles Road Overlay (Design)
WSDOT Region South Central
Legislative District 016
Congressional District 05
Project Description Reconstruct Bolles Road from Main Street to Waitsburg East city limits.
Project Type Design
Project Funding
Fund ProgramAmount
Freight Mobility$80,000.00
State Total$80,000.00
Other$0.00
Total Project Cost (see NOTE below)$80,000.00
Project Milestones
Preliminary Engineering Authorized 03-01-2024
Environmental Approved
Right of Way Certified
Construction Authorized
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.