Project Details

Project Details
Agency Montesano
Project # 5185001
Project Title Lake Sylvia Sidewalk - Phase 1
WSDOT Region Olympic
Legislative District 024
Congressional District 06
Project Description Install curb and sidewalk along Sylvia Lake Road including crosswalks, curb ramps, and minor drainage improvements.
Project Type Transportation Enhancement
Project Funding
Fund ProgramAmount
TAP$351,020.00
Federal Total$351,020.00
Other$319,980.00
Total Project Cost (see NOTE below)$671,000.00
Project Milestones
Preliminary Engineering Authorized 05-30-2023
Environmental Approved 11-15-2023
Right of Way Certified
Construction Authorized 07-01-2024
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.