Project Details

Project Details
Agency Medical Lake
Project # I320006
Project Title Lake St. ADA Upgrades
WSDOT Region Eastern
Legislative District 006
Congressional District 05
Project Description Replacement of existing non-conforming ADA ramps and driveway approaches.
Project Type Transportation Enhancement
Project Funding
Fund ProgramAmount
TAP$541,000.00
Federal Total$541,000.00
Other$0.00
Total Project Cost (see NOTE below)$541,000.00
Project Milestones
Preliminary Engineering Authorized 04-12-2023
Environmental Approved 04-30-2024
Right of Way Certified
Construction Authorized 09-17-2024
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.