Project Details

Project Details
Agency San Juan Co.
Project # 2028012
Project Title Town to Zylstra Lake Multimodal Trail
WSDOT Region Northwest
Legislative District 040
Congressional District 02
Project Description Construct walking and cycling pathway from Town of Friday Harbor to Zylstra Lake Preserve.
Project Type Transportation Enhancement
Project Funding
Fund ProgramAmount
Congress Directed Spending$5,280,000.00
Federal Total$5,280,000.00
Other$893,789.00
Total Project Cost (see NOTE below)$6,173,789.00
Project Milestones
Preliminary Engineering Authorized 06-13-2025
Environmental Approved 08-27-2026
Right of Way Certified
Construction Authorized 09-18-2026
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.