Agency
Spokane Co.
Project #
N326005
Project Title
Coulee Hite Road RR Crossing
WSDOT Region
Eastern
Legislative District
006
Congressional District
05
Project Description
Upgrade existing crossing with gates and flashing lights, installing guardrail to protect equipment, updating signs/markings and track crossing replacement. Including pavement repair at crossing. Also includes safety upgrades, and train-activated warning lights.
Project Type
Safety
Project Funding
Fund Program
Amount
Railroad
$1,503,433.00
Federal Total
$1,503,433.00
Other
$0.00
Total Project Cost (see NOTE below)
$1,503,433.00
Project Milestones
Preliminary Engineering Authorized
09-07-2023
Environmental Approved
09-18-2024
Right of Way Certified
Construction Authorized
03-05-2026
Completed
Roads
Satellite
JavaScript must be enabled in order for you to use this map.
However, it seems JavaScript is either disabled or not supported by your browser. To view this map, enable JavaScript by changing your browser options, and then try again.
LEGEND:
Design
Right of Way
Construction
Complete
Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.