Project Details

Project Details
Agency Kitsap Co.
Project # 18F2003
Project Title Newberry Hill Culvert Replacement
WSDOT Region Olympic
Legislative District 035
Congressional District 06
Project Description Replace undersized culvert on Little Anderson Cr at Newberry Hill Rd with a concrete box culvert designed for fish passage.
Project Type
Project Funding
Fund ProgramAmount
PROTECT$3,020,000.00
Federal Total$3,020,000.00
Other$157,515.00
Total Project Cost (see NOTE below)$3,177,515.00
Project Milestones
Preliminary Engineering Authorized
Environmental Approved 06-05-2023
Right of Way Certified 08-31-2023
Construction Authorized 09-13-2023
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed