Project Details

Project Details
Agency Pierce Co.
Project # 2203003
Project Title 264th St E. Culvert Repair
WSDOT Region Olympic
Legislative District 002
Congressional District 08
Project Description Replace failed culvert and restore roadway to pre-damaged conditions. Work includes dewatering, excavation, stream bed restoration, fabricating and installing a three-sided box culvert, backfilling, rebuilding the road base, paving, striping, and guardrail installation.
Project Type Preservation
Project Funding
Fund ProgramAmount
Emergency Relief (ER)$966,032.00
Federal Total$966,032.00
Other$160,668.00
Total Project Cost (see NOTE below)$1,126,700.00
Project Milestones
Preliminary Engineering Authorized 01-03-2023
Environmental Approved 03-19-2024
Right of Way Certified 08-27-2024
Construction Authorized 09-09-2024
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.