Project Details

Project Details
Agency Federal Way
Project # 000S673
Project Title High Friction Surface Treatment
WSDOT Region Northwest
Legislative District 030
Congressional District 09
Project Description Install high friction surface treatments on 16th Ave S, 10th Ave SW, S 349th St/Weyerhaeuser Way, S. 372nd Way/12th Ave, Redondo Way, and S. 372nd/Milton Rd.
Project Type Safety
Project Funding
Fund ProgramAmount
HSIP$952,000.00
Federal Total$952,000.00
Other$22,100.00
Total Project Cost (see NOTE below)$974,100.00
Project Milestones
Preliminary Engineering Authorized 11-21-2023
Environmental Approved 04-18-2024
Right of Way Certified
Construction Authorized 07-29-2025
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.