Project Details

Project Details
Agency Maple Valley
Project # 000S660
Project Title Stop and Speed Limit Sign Safety
WSDOT Region Northwest
Legislative District 005
Congressional District 08
Project Description Install solar powered stop and speed limit signs with perimeter flashing LED warning lights and radar speed feedback signs.
Project Type Safety
Project Funding
Fund ProgramAmount
HSIP$317,000.00
Federal Total$317,000.00
Other$0.00
Total Project Cost (see NOTE below)$317,000.00
Project Milestones
Preliminary Engineering Authorized 04-12-2023
Environmental Approved 04-11-2024
Right of Way Certified
Construction Authorized 08-22-2024
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.