Project Details

Project Details
Agency Maple Valley
Project # SR22007
Project Title SR 516 Pedestrian Crossing
WSDOT Region Northwest
Legislative District 005
Congressional District 08
Project Description Advance warning standard flashing beacons, marked crosswalk (includes illumination), rectangular rapid flashing beacons, ADA curb ramp retrofits, and safe routes to school walk or bike encouragement programs.
Project Type Transportation Enhancement
Project Funding
Fund ProgramAmount
Safe Routes to School$302,400.00
State Total$302,400.00
Other$68,600.00
Total Project Cost (see NOTE below)$371,000.00
Project Milestones
Preliminary Engineering Authorized 04-11-2023
Environmental Approved 01-25-2024
Right of Way Certified
Construction Authorized 05-07-2024
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.