Agency Lewis Co.
Project # 2021073
Project Title Railroad Switch Upgrade
WSDOT Region Southwest
Legislative District 020
Congressional District 03
Project Description Upgrade two manual railroad turnouts on the Washington Royal Line to Dual-Tone, Multi-Frequency power switches to reduce railroad and roadway freight delay times at the Blakeslee Junction rail crossing where it intersects Reynolds Avenue. 
Project Type Design
Project Funding
Fund ProgramAmount
NHFP$43,000.00
Federal Total$43,000.00
Other$7,711.00
Total Project Cost (see NOTE below)$50,711.00
Project Milestones
Preliminary Engineering Authorized 09-01-2022
Environmental Approved 09-06-2023
Right of Way Certified
Construction Authorized
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.