Project Details

Project Details
Agency North Bend
Project # 2817003
Project Title North Bend Bridge #3
WSDOT Region Northwest
Legislative District 005
Congressional District 08
Project Description Remove and replace the asphalt bridge deck over the South Fork Snoqualmie River.
Project Type Bridge
Project Funding
Fund ProgramAmount
Bridge$1,912,000.00
Federal Total$1,912,000.00
Other$0.00
Total Project Cost (see NOTE below)$1,912,000.00
Project Milestones
Preliminary Engineering Authorized 02-24-2023
Environmental Approved 04-12-2024
Right of Way Certified
Construction Authorized 02-12-2025
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.