Project Details

Project Details
Agency Lincoln Co.
Project # 2022089
Project Title Gerald Zellmer Bridge
WSDOT Region Eastern
Legislative District 013
Congressional District 05
Project Description Replace existing bridge and approach sections.
Project Type Bridge,Design
Project Funding
Fund ProgramAmount
Bridge$2,121,568.00
Federal Total$2,121,568.00
Other$0.00
Total Project Cost (see NOTE below)$2,121,568.00
Project Milestones
Preliminary Engineering Authorized 03-16-2023
Environmental Approved 07-08-2026
Right of Way Certified
Construction Authorized 09-18-2026
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.