Project Details
Agency Lacey
Project # 5284002
Project Title Willamette Dr/Campus Glen Roundabout
WSDOT Region Olympic
Legislative District 022
Congressional District 10
Project Description Construct traffic control roundabout.
Project Type Design
Project Funding
Fund ProgramAmount
STP Regional$216,250.00
Federal Total$216,250.00
Other$33,750.00
Total Project Cost (see NOTE below)$250,000.00
Project Milestones
Preliminary Engineering Authorized 03-21-2022
Environmental Approved
Right of Way Certified
Construction Authorized
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed